Date: August 5, 2009
To: Board Finance Committee
From: M. McCathy-Anderson Chair
RE: 2010 city budget options
New direction for the 2010 city budget was received on July 10. I have attached the budget file and included below is a chart outlining the costs related to Option 1. Additional option narratives are provided in priority order below as well.
|
City Library Budget |
2009 |
2010 |
|
2010 |
|
|
|
|
Mayor |
Variance |
Library |
Impact |
|
Current Status |
2,733,453 |
2,699,189 |
|
2,699,189 |
|
|
Supplemental Board Funds |
37,490 |
|
28,587 |
66,077 |
|
|
Total General Fund |
2,705,483 |
2,699,189 |
|
2,765,265 (Option 1) |
Hiring freeze - one FTE, deferred facilities maintenance, elimination of paper notices for overdues and holds, cancel 3 databases, additional CIP funding to complete acoustics final phase |
|
Remaining non budgeted Board Funds |
18,009 |
|
|
8,820 |
Designated to acoustics final phase |
Option 1: Eliminate 3 databases that have less use when compared to others; delay acoustics project until 2010; supplement 2010 city budget in the additional amount of $28,857 from Board Funds budget for a total of $59,557 for ongoing operational costs.
· Cancel 3 databases: $17,840
· Acoustics project delayed until 2010
o Anticipate 2% cost increase due to delay
o Would reduce amount available for acoustics to $10,000
§ $30,000 plus the 2% increase would be needed from CIP
Option 2: Supplement 2010 city budget in the amount of $38,557 from Board Funds budget;
· This would eliminate the reserve from the Board Funds budget
· Acoustics project delayed until additional funding is available
Option 3: Reduce downtown library hours and cut one staff
· Decrease from 68 hours per week to 64 per week
o Anticipated cost savings of $4,700
o Hours at RCPL-North would not be changed – because of the operation as a school library, North operates at an average of 38 hours per week
· Freeze/eliminate one FTE staff
o Anticipated cost savings in wage and benefits, $33,611