Date: September 10, 2008
To: RCPL Board of Trustees
From:
G. Chapman
Re: Strategic planning timeline
Date: September 2, 2008
To: Greta Chapman
From:
Terri Davis
Re: Strategic plan work
groups and timeline
In
order to implement the updated Strategic Plan, a number of workgroups have been
established. Staff was assigned to
various workgroups based on their interests and roles, and an initial timeline
was outlined.
After
reviewing the timeline, it was identified that the proposed schedule was faster
than can be accomplished while accommodating other library programs and
events. Therefore, the schedule was
adjusted to move some projects farther into 2009.
With
the updated timeline, the overall implementation of the Strategic Plan can be
accomplished by 2010 as planned.