610 Quincy St. Rapid City, SD 57701

605-394-6139

www.rapidcitylibrary.org

 
 

 

 

 

 

 

 


Date:   April 2, 2008

To:       RCPL Board of Trustees

From:   Greta Chapman

Re:       March 2008 Budget Narrative

 

Date:   April 2, 2008

To:       Greta Chapman

From:   Kimberly Hodgson, Administrative Assistant

Re:       March 2008 Budget Narrative

 

The Library estimates spending approximately 8.3% of its budget on a monthly basis. Expenditures are on track for 2008 with 77.22% remaining of the City budget, 91% remaining of the County budget and 83.13% remaining in the Board Funds budget.

 

The following is a list of line items of interest for each budget:

 

I.       City Budget

  • 4270 – Travel & Training – 69.81% remaining
    • The costs for this line item are high due to conference travel and training for the staff and Board. However, because expenses for this line item have been budgeted for the entire year, expenditures are on track.

 

II.    County Budget

We are on track for County budget expenditures to date.  At this time there are no line items for review. 

 

III. Board Funds Budget

To date expenses have been minimal out of the Board Funds Budget.  At this time there are no line items for review.

 

IV. Previously Discussed City Budget Items

·         4210 – Insurance – 49.12% remaining

o    These are fixed costs and we are on track for the year.

·         4220 – Professional Services – 82% remaining

o    The expenditures in this line item are high due to the first quarterly payment made to the South Dakota Library Network.  We are on track for expenditures in this line item for the year.

·         4230 – Publishing – 33% remaining

o    Due to vacancies related to the county contract, two employees transferred to city openings during negotiations, advertising for those vacancies have used funds from this line item.

·         4240 –  Rentals – 84% remaining

o    Maintenance and service contracts approved shall renew at the beginning of each calendar year thus increasing the expenditures in this line item at this time. 

·         4250 – Repair & Maintenance – 51% remaining

o    Johnson Repair maintenance contract has been signed as we have a January to December agreement.  Also, the 3M Self Check Machine contract came out of this line item as a clerical error.  The funds will be supplemented back into the appropriate

line item by city finance.

 

 

 

    EQUAL OPPORTUNITY EMPLOYER