610 Quincy St. Ÿ Rapid City, SD  57701

605-394-4171 Ÿ www.rapidcitylibrary.org

 

Date:   May 8, 2006

To:       RCPL Board of Trustees

From:   E. Abrahamson, Chair

            Building Committee

Re:       Space Use Plan and School Community Center Report 

 

Recommendation:

Space Use Plan – Coffee Shop and Carpet Replacement with Carpet Tiling

§    Enter into a contract with a coffee vendor.

§    Expend from Board Funds $28,775 to implement the first phase of the space use plan.

 The first phase would include the coffee shop and completion of carpet replacement that includes the carpet tiling plan. The Board Fund designates $35,950 for furniture and building/structures that could be utilized for the coffee shop remodeling and carpet tiling. There is an approximate ending balance of $70,000 currently in the account.

 

Joint Meeting School Board and Council Update: School Community Center at General Beadle

Two joint meetings of the City Council (five each time), School Board representatives and RCPL Building Committee members are being scheduled for the week of May 30. These meetings are replacing the Council Informational Meeting to allow a more thorough review of combined projects between the City and the School. The School Community Center at General Beadle will be discussed at this time for feedback from all parties involved. 

 

Combined Funding Resources with a Two Year Phased in Implementation

The Building Committee also discussed an approach of phasing in the project given the total amount and resources for implementation. In addition to the designated Board Funds, public funding for the 2007 City Budget Justification form would prioritize $50,000 of the $300,000 for service points and the Technology Commons. The Technology Commons space includes equipment for community archiving/digitization and computer access to online resources. A proposed timeline has been initially discussed with the Foundation to raise the $200,000 from now until September 2007. This would allow for the remaining public funding to be allocated in 2008.    

 

Background:

Summary and estimates received by Space Use Consultant George Lawson are included with this memo. Implementation of the proposed space use reconfiguration needs to be outlined on a timeline; preliminary steps are being taken by staff to compile this information.  Two primary initial actions need to take place, and scheduling of subsequent implementation activities is dependent on those.

 

The first step of the implementation would be the installation of the coffee shop at an estimated cost of $14,775.  The events that need to occur for this to happen are:

1)      Recommendation and approval of a vendor contract for the coffee shop

2)      Update the Genealogy Society on proposed location for their collections (this occurred on 4/21/06, and the information was favorably received by the Society).

3)      Permits for building and electrical – Library Facilities Maintenance Supervisor

4)      Health Department and Sales Tax License – Vendor

5)      Fire Department and ADA regulations – Public Services Manager

6)      Install plumbing, wiring, and new flooring for the coffee shop – Contractors

a.       Cost estimate is $4085 for plumbing and electrical

                                                              i.      Estimates for flooring still need to be determined $5,200

b.      Crossroads Coffee will pay for the counter and all equipment

c.       Furniture costs are estimated at $5,490 – Library Staff

 

The second project is replacement of the remaining old carpet under the stacks and installing the carpet tiling plan. Total cost is $15,000. At a later date due to available funding, another installation would take place for the curved path carpet but the stack mover would not be necessary.  Because of scheduling with the carpet installers and the stack moving equipment, the first phase of carpet replacement is anticipated for September.

 

 

    EQUAL OPPORTUNITY EMPLOYER