Date: November 14, 2005
To: RCPL Board of Trustees
From: G. Chapman
Re: Satellite Library Site Fire Station # 7
Date: November 14, 2005
To: G. Chapman
From: T. Davis
Re: Satellite Site Fire station #7 Update
Discussions have been continuing
internally originating from the 2012 proposal of combined library, Fire and
Police services. Sites being discussed are the existing Fire Station on Haines
and
On October 31, C. Ramirez and T. Davis met with Fire Chief Gary Shepherd and Building Inspector Brad Solon at Fire Station 7. The purpose of the meeting was to evaluate the fire station’s lower level that opens to the outside for possible future use as a library satellite facility.
Overall, the space could be
functional for a satellite library facility of approximately 700 square feet.
Given its proximity to
Use of the space for a library
facility would require some renovation, including modification to the 2nd
exit, making the doorway
Parking on the site is tight but
possible. We would have access to two regular and one
Zoning is being reviewed to determine if a library can operate in a shared fire station facility. Estimated remodeling costs will also be determined by the beginning of 2006, as a means of consideration into the 2007 Budget if this project is to continue to move forward.