Date:   November 7, 2005

To:       RCPL Board Finance Committee

From:   G. Chapman

Re:       2005 End of the Year Budget Report

            Recommendation for Bid Process

 

Recommendation:

            Pending Finance Department review; approve for bid the final phase of carpet replacement and phase one of the acoustical plan. Also approve for purchase a carpet extractor. 

 

Background:

Projected Fund Balance

In the chart included are the remaining purchases for this year’s facilities and equipment replacement items. Also recommended are items that are not planned for this year’s budget. If the carpet replacement and phase one of the acoustical plan is approved because of the total cost the Board would also need to approve a bid process for each one. These bid items are a part of the Library Strategic Plan goals and have been reviewed previously.

 

The facility line items in the current budget will be over due to the remaining expenses and to uncontrollable costs of vandalism and equipment failures. However, city financial procedures allow for line items to be over if the ending balance is within budget and the items for purchase were scheduled in the existing budget. The non budgeted items are in review with City Finance and I am planning to give an update at the Board meeting. However, these two items have been requested previously in a funding process. The carpet is scheduled for the 2007 Budget Cycle and the acoustical plan has been reviewed by the Capital Improvements Plan (CIP) but denied at this time based on other priorities. 

 

The facilities maintenance plan continues to be updated for the space built in 1972. Due to financial impact, the implementation is being phased in, as no previous plan existed. The vandalism has been addressed in a previous report for preventive measures.

 

Non Budgeted Items

The Finance Department review is based upon the City procedure of a portion of revenue for the city budget and is built upon end of the year funding returned by departments. The annual return from the library budget has been approximately $10,000 or less with the exception of one year that was $80,000 due to estimated funding for health benefits. The actual cost was not known until after the budget was set. If expenditures for the non budgeted items are approved the end of the year funding returned to the City General Fund would still be higher than average at approximately $34,500. 

 

The remaining funding is due to costs that are estimated two years in advance and vacancy savings as staff changes occur. The non budgeted amount of $ 61,500 is recommended for purchasing the final stage of carpet replacement, a carpet cleaner extractor, and begin phase one of the acoustical plan.     

 

Remaining Annual Return (after budget and non budget expenditures)

$  34,000

 

 

Budget Items to be purchased:

Facilities:

 

  • Tree trimming (not done since planting)

$  1,200

  • Final phase of paint – TS workroom and Hoyt

$  7,000

  • Complete landscaping around all plants

$  4,000

Replacements:  Equipment/Existing Building

 

  • 3M security gates

$ 11,422

  • Final phase ceiling replacements (4)

$ 10,675

  • Audio/Media replacement shelving

$  8,550

  • Meeting Room Accordion Closet Door broken-replacement

$  1,300

 

 

Non budgeted Items recommended for purchase:

 

  • Final stage of carpet replacement

Carpet cleaner extractor

(requested in 2006, scheduled 2007)

$ 39,000

$  2,500

  • Acoustics remediation

$ 20,000

________

 

$ 61,500